A model for the investment costs for the procurement and installation of the off-shore platform: (2/3)⋅(0.4⋅10^−3⋅m_jacket^2 − 50⋅m_jacket − 80⋅10^6), with m_jacket = 582⋅d_water^0.19⋅(3⋅10^−3⋅P_farm,rated + 0.5⋅10^6)^0.48 [2003 SEK].
Open in the explorer → Suggest an edit
Cite the database: Quaeghebeur, E., Sanchez Perez-Moreno, S., and Zaaijer, M. B.: WESgraph: a graph database for the wind farm domain, Wind Energ. Sci., 5, 259–284, 2020. doi:10.5194/wes-5-259-2020