switch gear procurement cost

A model for the investment costs for the procurement of the switch gear, charging a cost per cubicle at the turbines, at the collection and transmission sides of the platform, and at the grid connection point: (100.33⋅10^3 + 2.8726⋅V_L,infield)⋅N_cubicles,turbines + (320⋅10^3 + 6⋅V_L,infield)⋅N_cubicles,collection + (320⋅10^3 + 6⋅V_L,transmission)⋅N_cubicles,transmission + (320⋅10^3 + 6⋅V_L,grid)⋅N_cubicles,connection [2003 SEK].