A model for the investment costs for the procurement of the switch gear, charging a cost per cubicle at the turbines, at the collection and transmission sides of the platform, and at the grid connection point: (100.33⋅10^3 + 2.8726⋅V_L,infield)⋅N_cubicles,turbines + (320⋅10^3 + 6⋅V_L,infield)⋅N_cubicles,collection + (320⋅10^3 + 6⋅V_L,transmission)⋅N_cubicles,transmission + (320⋅10^3 + 6⋅V_L,grid)⋅N_cubicles,connection [2003 SEK].
Open in the explorer → Suggest an edit
Cite the database: Quaeghebeur, E., Sanchez Perez-Moreno, S., and Zaaijer, M. B.: WESgraph: a graph database for the wind farm domain, Wind Energ. Sci., 5, 259–284, 2020. doi:10.5194/wes-5-259-2020
This page: https://wesgraph.anemona.io/concept/switch-gear-procurement-cost-model/